2023 Student Research Case Study Challenge: Relocation Social Insurance

city

source: https://cdn.dribbble.com/users/330915/screenshots/3882301/media/d930615ad8352da62c7ae89fb800525f.gif

UNSW x SOA sponsored by Valani Global

alt text

Group JKB Consulting Report

Members: John Mckinnon, Karen Chan, Benjamin Quek

The purpose of this page is to outline the key insights and analysis of the proposed scheme to address displacement risk as a result of climate impacts for Storlysia. For access to the full report and relevant codes, please click on the buttons below.

2023 SOA Case Study CONSULTING REPORT FINAL COMBINED CODE


Executive Summary

Objectives

Program Design

Pricing and Costs

Assumptions

Risk and Risk Mitigation Strategies

Data and Data Limitations

Conclusion/Recommendations

References


Executive Summary

This report was composed to design and evaluate a social insurance program to assist Storslysia in mitigating displacement risk as a result of climate-related hazard events. The program design specifies claim coverage of 30% of household goods and 12 months of temporary housing, as well as incentives such as buybacks and grants to provide opportunities for voluntary relocation to lower risk regions. Projections of economic costs over short- and long-term time frames with and without the proposed insurance program found that the scheme was able to reduce displacement costs with a high degree of certainty in the long-term under all climate scenarios. The economic capital needed would be at least φ 300 billion each year to remain solvent, but the scheme remains within 10% of GDP with 97.5% confidence. Moreover, the key risks were assessed through both qualitative and quantitative risk analyses, with suggested mitigation strategies. The report concludes with a recommendation of how to proceed with the implementation of the program based on the analyses performed.

Objectives

The goal of this social insurance program is to manage the financial risks associated with catastrophe-related displacement in Storslysia. To this end, the program aims to encourage proactive relocation which lowers damage risk and comes at a lower cost than involuntary displacement. This scheme will cover the entire population of Storslysia. As well as reducing long-term costs from climate-related disasters regardless of future emissions scenarios, this scheme will provide financial support to Storslysia citizens affected by such disasters. This program will be equitable in its design such that very affluent households are not advantaged by the scheme any more than lower or middle-class households. Keeping the costs arising from relocation from exceeding 10% of GDP each year with a high degree of certainty is the aim of this program.

The following key metrics will be used to monitor the social insurance program:

Metric Frequency
Compare costs with and without the scheme Annually for the first 10 years, then every 3 years
Number of people who voluntarily relocated each year Annually
Cost as a percentage of GDP Annually
Value at risk Annually

Program Design

In our program, all citizens of Storslysia will be covered for displacement costs after a climate catastrophe. However, we will distinguish between support for households who are voluntarily relocating and households who are involuntary relocating due to a natural disaster. We also distinguish between renters and owner-occupiers.

Requirements to make a claim

All households, regardless of region, are entitled to financial support for temporary housing, rebuilding their property and household-goods replacement costs. For households in regions 2, 4, 5 and 6, additional support is provided contingent upon that household relocating to regions 1 or 3, the lower risk regions. (See report Appendix Table 2.1 for justification of which regions are high and low risk). To be eligible for voluntary relocation support, a household in a highly affected region (regions 2, 4, 5 and 6) may apply for financial assistance to relocate their household to a safer region (regions 1 or 3). Both renters and owner-occupiers in highly affected regions are eligible for this support. To be eligible for involuntary relocation support, a household in regions 2, 4, 5 or 6 must be affected by a severe weather event, causing irrecoverable damage to the home such that it is no longer fit for living.

fast flood

source: https://guillaumekurkdjian.com/wp-content/uploads/2017/06/C_house_dribbble.gif

Program coverage

Support for all households with uninhabitable homes affected by the natural disaster, regardless of the region, include the following:

In addition, the following benefits are included as a part of the program to assist with relocation:

  Voluntary relocation Involuntary relocation
Owner-occupiers (Region 2,4,5,6) Pay for construction of new home (up to median value) + lump-sum of φ 10,000 Buy back uninhabitable homes (up to median value) provided the household moves to a low-risk region
Renters (Region 2,4,5,6) Pay for home rental costs for 6 months (up to median rent) Pay for home rental costs for 2 months in the new region (up to the median rent)

new condo

source: https://cdn.dribbble.com/users/330915/screenshots/6554409/1_new_condo.gif

Pricing and Costs

Methodology

To accurately project the economic costs of the climate-related catastrophes for Storslysia, data was gathered from Storslysia’s quarterly historical record of climate-related catastrophes ranging from 1960 to 2020, as well as economic and demographic data on each of the 6 regions. Exploratory data analysis was performed to understand the economic and demographic nature of each region and their climate risks. A training set of data was selected for the period 1960 to 2015, leaving the last 5 years as a validation set to assess performance via various metrics. Taking a frequency-severity approach to pricing claims cost, forecasts were projected for each region using simulations from each distribution, before aggregating to a final estimate with 97.5% confidence intervals.

Short-term projections - average over the program’s first 10 years

Economic costs

Without the proposed insurance program, the cost of total property damage is estimated to be close to φ 255 million per annum. Along with property damage, climate-related catastrophes also come with additional costs, including temporary housing for involuntary relocation, material and labour for rebuilding damaged properties, and replacing household items. These costs have been summarised in the table below as displacement costs. The short-term projection (2020-2030) for total economic cost is φ 836.6 million per annum.

  Mean Estimates Upper Bound (97.5%)
Property Damage φ 255,115,548 φ 9,637,762,244
Displacement Costs φ 581,450,888 φ 25,738,567,833
Total Economic Costs φ 836,566,436 φ 35,376,330,076

Program costs

Under the proposed social insurance program, residents in high-risk areas (Region 2, 4, 5, 6) will be incentivised to move both before and after a hazard event occurs. This corresponds to the voluntary and involuntary costs below, respectively. In the short-term, this program will lead to higher economic costs due to extra payments to incentivise residents to move to lower-risk regions through lump-sum payments, construction of new homes, rent payments and house buy-backs (see Program Design section for full details).

From the projected values below, a slight reduction in the mean property damage and displacement cost estimates is evident, compared to costs without the program (11.6% and 6.9% respectively). Additionally, in the short-term (2020-2030), the cost of incentivising voluntary relocation is around φ 12 billion, while involuntary relocation after a hazard event is only around φ 55.5 million. As the number of voluntary relocations declines, the scheme costs will also decline.

  Mean Estimates Upper Bound (97.5%)
Property Damage φ 225,302,571 φ 8,968,316,447
Displacement Costs φ 514,378,676 φ 23,953,318,562
Relocation Incentive Costs φ 12,310,238,772 φ 12,310,238,772
Voluntary Costs φ 12,254,805,736 φ 12,254,805,736
Involuntary Costs φ 55,433,035 φ 55,433,035
Total Economic Costs φ 13,049,920,018 φ 45,231,873,780

Long-term projections

Program costs

With the social insurance program in place, the effects of incentivising relocation will continue to be experienced and reduce the overall property damage and displacement costs. Averaging over 10 years of economic costs (i.e. 2070-2080), gives the values in the table below. Both the mean and upper bound estimates for property damange and displacement costs are significantly lower than without the program (12.6% and 10.9% respectively). Moreover, the incentive cost for voluntary relocation is under φ 200,000, suggesting that the equilibrium population allocation in each region has almost been reached. The average displacement costs have also decreased another 8% from the initial short-term projection.

  Mean Estimates Upper Bound (97.5%)
Property Damage φ 206,962,717 φ 8,570,367,393
Displacement Costs φ 473,142,809 φ 22,892,334,372
Relocation Incentive Costs φ 51,065,396 φ 51,065,396
Voluntary Costs φ 174,906 φ 174,906
Involuntary Costs φ 50,890,490 φ 50,890,490
Total Economic Costs φ 731,170,922 φ 31,513,768,160

Capital and solvency requirements

According to the European Union’s Solvency II requirement, companies must hold enough capital to have a 99.5% confidence of surviving the most extreme expected losses during a year (Risk.net n.d.). To ensure this same level of certainty for Storslysia’s insurance program, the total economic capital in the first year of implementation would be close to φ 390 billion. After that, each subsequent year requires less capital to be held ending at around φ 346 billion needed in 2110. The amount of capital needed over the short and long-term timeframes is displayed in the graph below.

Capital Requirement Graph

Assumptions

Assumptions within the modelling process, economic climate and validity of the utilised datasets were required to ensure the program generated accurate and reliable results. A summary of all the assumptions used can be seen in the table below.

# Assumption Explanation
01 Population Closed population model (based on 2021 population)
02 Voluntary relocation 4% of households voluntarily relocate each year, decreasing by 20% per year
03 Displacement 20% of households impacted by climate event will relocate
04 Temporary housing Only needed for 12 months after a hazard event which is adequate time to rebuild a house to a liveable state
05 Inflation Average material and labour inflation after a hazard event is 25%, while in the more severe scenarios is 50%; no inflation for voluntary relocation
06 House contents Value as proportion of house value is based on ABS data, average cost of replacing increases by 57.5% after a hazard event, with the more severe case of 75%
07 Median value Property values of each region are estimated by median value
08 Property damage Increases/decreases are proportional to the changes in population in the region
09 Model Chosen frequency and severity models are correct
10 Interpolation Data can be accurately interpolated via linear or geometric mean

Risk and Risk Mitigation Strategies

Key risks and mitigation strategies

When a project is underway, unexpected factors have the potential to affect the success of a project, and thus proactive identification, assessment and action improves the chance of success in meeting project objectives (Hillson, David 2014). The risk matrix (below) illustrates the key areas of risk present within the scheme, and is accompanied by an explanatory table:

Risk Matrix

Risk Description Mitigation
A: Event Risk Risk that future climate events result in damages deviating from model predictions; regions may not be homogeneously affected by climate change and new homes in regions 1 and 3 may have different risk profiles from existing homes Monitor model predictions versus actual property damage on a regular basis; perform sensitivity analysis at the 97.5% event-risk level and hold recommended capital reserves at the 99.5% risk-level
B: Legislative/ Governance Risk Frequency and severity of climate events are contingent upon governments’ climate policies; political and governance changes may require modifications to the scheme Close analysis and discussion with Storslyia’s government annually to determine if the scheme is still adequate; consider impact different climate scenarios
C: Inequality Risk Risk that the scheme exacerbates or creates inequalities by disproportionately assisting citizens of higher socio-economic status who are often owner-occupiers Specific schemes to assist lower-income and wealth individuals and limit the maximum amount paid (such as paying up to the median value of properties in the new region); monitoring people who take up the scheme and modifying it to make it more equitable
D: Migration Risk Program’s ability to induce relocations from one region to another is constrained by household decision making, affecting the economic success of the scheme Financial compensation provided to incentivise relocations, which will be reviewed and updated
E: Prediction Risk Difficulty in projecting for long-term timeframes of up to 100 years, resulting in volatile forecasts and affecting capital allocation and scheme costing Conservative approach taken in claims modelling and in assumptions; sensitivity analysis performed to consider impact of varying scenarios

Sensitivity analysis

The sensitivity analysis is performed using the Shared Socioeconomic Pathways (SSPs) carbon emissions scenario forecasts (see Appendix Table 3.2). The projected log values of the long-term economic costs without the program are shown in the graph below. Under the best scenario (SSP1) where the world shifts to become greener and more sustainable, then the costs of climate-related disasters can be reduced below current (2020) levels. However, in the other 3 scenarios of higher carbon emissions, the economic cost will only continue to increase in the future. In the most severe scenario (SSP5), the average economic cost could increase up to 17-fold by 2150.

Certainty of cost estimates

Under the proposed program, there is a 97.5% confidence that costs will not exceed 10% of Storslysia’s GDP in any given year as seen in the graph below. The solid lines represent the scheme cost and dashed lines represent 10% of GDP, each under the four SSP scenarios. The real GDP is modelled assuming no population growth and only increases in GDP per capita. While the scheme does not exceed 10% of GDP between now and 2100, there is the possibility it may exceed this level after 2100, particularly in the SSP5 scenario. This means that the program and underlying model assumptions must be assessed in the future to ensure it remains sustainable beyond around 80 years.

Given constant claims (no adjusting for climate scenarios), the scheme is expected to have a negative economic benefit for 26 years. After this, the scheme delivers benefits increasing to $110 million in reduced damage and displacement costs per year. Under higher claims scenarios, the economic benefits of the scheme increase:

The success of the scheme depends on the take-up of the voluntary relocation program, the main driver of reduced risks and reduced damage and associated costs. Secondary research suggested that between 15-20% of people would consider relocating to be away from high-risk areas without any additional financial incentive; hence, our 20% estimate of voluntary relocation is rather conservative, and take-up may be even higher (Yazzie R. 2021).

Data and Data Limitations

Data Sources

In addition to the Storlysia-specific data – housing and demographic information, historical weather-related hazards data and macroeconomic data – external data from the ABS (Australiabn Bureau of Statistics) was also utilized to inform the modelling process.

Limitations of provided data

There are inherent data limitations which inhibit the predictive capacity of the program and hence reliability. Operational risks as a result of human error when inputting, duplicate or missing values and one-off extreme values in historical data (e.g. inflation values in 2003) have impacts in the training of the model. To overcome these limitations, interpolation via linear or geometric means using surrounding data was utilised where appropriate. The rationale for this was due to calibrate the model without the influence of severe outliers.

Limitations when utilising data

The inability of historical data to perfectly capture population movements and account for unique situations within the future also presents a limitation in the modelling process, thereby limiting the accuracy of our program analysis. This is especially prevalent within the climate modelling area which has seen impacts in frequency and severity exacerbated by climate change. Compilation of data and the period of impacts has also presented a limitation as hazard event data only accounts for property damage (and does not distinguish between household goods, and material and labour costs) which is recognized and measured in days (duration). More precise calculations of property damage as well as duration of the hazard event would thus increase the predictive capacity of the models, as well as more data points to train the frequency and severity models.

Conclusion/Recommendations

In conclusion, the proposed social insurance scheme can help Storslysia mitigate their climate-related displacement risk while remaining under 10% GDP with a high level of confidence. After extensive analysis on the impact of the social insurance program over short and long-term timeframes and under different climate scenarios, the improved financial and social benefits associated with the scheme provide substantial evidence that the project should be undertaken given our assumptions. Although there are risk mitigation analysis and monitoring protocols incorporated within the program design of the scheme, it is quintessential to verify the plausibility of assumptions to ensure the validity and success of the scheme in achieving its objective to manage the financial risks associated with catastrophe-related displacement in Storslysia. The viability and strategy of financing the scheme must also be considered.

References